Before the UHV and key power grid projects of the

2022-08-16
  • Detail

In order to implement the spirit of the fifth session of the third workers' Congress of the State Power Corporation of China and the 2020 work conference, strengthen the efforts to make up for weaknesses in the field of infrastructure, give full play to the important role of key power projects in high-quality power development, clean energy consumption, power targeted poverty alleviation and other aspects, and meet the power demand of economic and social development, according to the national development and Reform Commission According to the work arrangement of the 13th five year plan for power development issued by the national energy administration, in accordance with the working idea of focusing on and efficiently promoting the cascading system, including a high-voltage cooling suppression cycle and a low-voltage cooling suppression cycle, the State Power Corporation of China has studied and prepared the preliminary work plan for UHV and trans provincial 500 kV and above AC and DC projects in 2020

I. preliminary work plan of UHV power project

(I) UHV AC project

1 Nanyang Jingmen Changsha project. The Ministry of development of the people's Republic of China organized and completed the relevant special research in February and obtained the approval in March

2. Nanchang Changsha project. Jiangxi and Hunan electric power obtained provincial supporting documents in April; In April, it obtained the preliminary review opinions of Nanchang Station land of the Ministry of natural resources; The Ministry of national development submitted a request for approval in May and received an approval in June

3. Wuhan Jingmen project. Hubei electric power obtained the provincial approval supporting documents in July and submitted them to the Hubei Provincial Development and Reform Commission for approval, and obtained the approval approval in September

4. Zhumadian Wuhan project. Hubei electric power obtained provincial supporting documents in July; The Ministry of national development submitted a request for approval in July and received an approval in October

5. Wuhan Nanchang project. Hubei and Jiangxi electric power obtained provincial supporting documents in September; The Ministry of national development submitted a request for approval in October and received an approval in December

(II) UHVDC project

1 Baihetan Jiangsu project. In March, Sichuan, Hubei and Anhui electric power obtained provincial approval supporting documents; The Ministry of national development submitted a request for approval in April and received an approval in June

2. Baihetan Zhejiang project. In September, Sichuan, Chongqing, Hubei, Anhui and Zhejiang electric power obtained provincial approval supporting documents; In October, the Ministry of natural resources obtained the preliminary review opinions on the land for converter stations at the sending and receiving ends: the Ministry of national development submitted a request for approval in October, and obtained the approval reply in December

3. Jinshang hydropower transmission project. The Ministry of national development completed the pre feasibility study of the project in June; After being incorporated into the national power planning, the feasibility study and design integrated bidding will be carried out

4. Longdong Shandong project. The Ministry of national development completed the pre feasibility study of the project in June; After being incorporated into the national power planning, the feasibility study and design integrated bidding will be carried out

5. Hami Chongqing project. The Ministry of national development completed the pre feasibility study of the project in June; After being incorporated into the national power planning, the feasibility study and design integrated bidding will be carried out

II. Preliminary work plan for key projects such as improving the efficiency and benefits of UHV channels

1 Wuhu UHV substation expansion project. Anhui electric power was responsible for the feasibility study and preliminary work, which was approved in March 2020

2. Shanxi Jinbei UHV substation expansion project. Shanxi electric power was responsible for the feasibility study and preliminary work, which was approved in June 2020

3. Shanxi Jinzhong UHV substation expansion project. Shanxi electric power was responsible for the feasibility study and preliminary work, which was approved in June 2020

4. Inner Mongolia Huineng Changtan power plant transmission project. Guomengdong power was responsible for the feasibility study and preliminary work, which was approved in June 2020

5. Inner Mongolia Jungar Suancigou Power Plant Phase II transmission project. Guomengdong power was responsible for the feasibility study and preliminary work, which was approved in August 2020

6. Beijing East UHV substation expansion project. Guoji north power was responsible for the feasibility study and preliminary work, which was approved in December 2020

7. Lhasa Converter Station Condenser expansion project. China Tibet electric power is responsible for the feasibility study and preliminary work, and obtained the feasibility study approval in May 2020

8. Shanxi West to East power transmission channel adjustment and other projects. Led by the North China branch, with the cooperation of Shanxi, Hebei and Hebei electric power, it strives to be approved by June 2020

9. Wuhu sanhuifengshan 500 kV double circuit line capacity expansion and reconstruction project. Led by the East China branch and coordinated by Jiangsu and Anhui electric power, it was approved in June 2020

10. Fujian Guangdong joint project. Led by China Fujian electric power, the establishment of the joint venture was completed in May 2020: led by the Ministry of national development, with the cooperation of East China branch and China Fujian electric power, it was approved in August 2020

11. Bahrain Naiman Fuxin 500 kV AC power transmission and transformation project. Under the leadership of Northeast China branch and the cooperation of guojiangning Mengdong Electric Power Co., Ltd., it strives to obtain approval in October 2020

12. Construction power supply project of Changdu Linzhi section of Sichuan Tibet railway. Tibet Electric Power Co., Ltd. was responsible for the feasibility study, which was completed in June 2020 and approved in November

13. Guolong wusheng 750kV III circuit line project. With the cooperation of Gansu and Qinghai electric power, the leading countries of Northwest China branch, we strive to obtain approval in December 2020

III. preliminary work requirements for 330kV and above power projects

first, strictly implement the national power plan. The state has launched the preparation of the 14th five year plan for electric power, and the company has prepared the 2019 version of the power plan to determine the power projects from 2020 to 2022. For the power projects that have been included in the company's plan but have not been included in the national plan, all units can carry out the project feasibility study and preliminary work first, and submit the approval request after being included in the national plan; For power projects not included in the company's planning, all units shall not start the feasibility study and related preliminary work

second, effectively improve the efficiency and benefits of the project. All units should give priority to the power projects to improve the UHVDC transmission capacity. For the frame optimization project of transmitting the UHVDC supporting power and improving the DC transmission capacity in operation, it is necessary to open up a green channel, compress the preliminary work processing cycle, and obtain approval as soon as possible; For its new UHV DC supporting power project compared with carbon fiber composite materials, according to the principle of synchronous planning, synchronous construction and synchronous production, the preliminary, investment and construction work plans are formulated as a whole to ensure effective connection

third, carefully prepare the spatial layout plan of power facilities. All units should comprehensively sort out the needs of power construction projects, prepare the spatial layout planning of trans provincial and trans regional transmission of 220 kV and above, and distribution power facilities of 110 kV and below, and strengthen the precise docking of power planning with national and local development planning and land and space planning according to the requirements of one port external level by level docking, and fully consider local government planning, land use, transportation, environmental protection, overburden minerals and other factors, Ensure that the projects included in the plan are timely, complete and accurately included in the land and space planning at all levels

fourth, comprehensively strengthen the integrated management of feasibility study design. At present, except for some provincial units, the company system has carried out the integrated management of feasibility study and design of power projects, and the feasibility study quality, work efficiency, professional connection and other aspects have been effectively improved. In the next step, all units should strengthen the integrated management of feasibility study and design, and clarify the division of labor and optimize the workflow in accordance with the measures for the management of feasibility study of power projects of national household appliances Co., Ltd. from a domestic perspective (Trial) (rules and regulations No.: National (development/2)), Strengthen the design, review and quality management in the feasibility study stage, ensure the consistency of the feasibility study and design technical scheme, and effectively improve the quality of the feasibility study design

fifth, give full play to the role of segment support management. As an important part of the feasibility study and preliminary work management of power projects, the division should play a practical role. It is mainly responsible for organizing and carrying out the feasibility study of cross provincial 750 and 500 kV power projects and headquarters and divisional expansion power projects in the region, participating in the feasibility study and preliminary work of UHV projects in the region, and at the same time, carrying out verification and evaluation for the planning and implementation of feasibility study approval of 330 kV and above power projects in the province, and the reasonable compliance of major technical principles, Relevant information shall be reported to the headquarters in time

all units often divide the power spectral density curve into several rectangular and triangular 00 kV and above AC and DC project preliminary work plans according to the company's power project preliminary work management measures and the above UHV and trans provincial 5, and submit official documents to the company's headquarters for filing before March 10